Try these free PK0-005 sample questions for CompTIA Project+, with an answer and explanation for each one. They include change control, risk and project charts. Use them to find the phases of the project life cycle you need to review.

Try them in the simulator Same questions, with study, timed and flashcard modes.

Showing 14 of 29 free sample questions.

Question 1Choose one

True or False: In a SaaS (Software as a Service) project implementation, the customer is responsible for managing the underlying physical infrastructure, including servers and storage.

Question 2Choose one

A project manager is reviewing the Environmental, Social, and Governance (ESG) criteria for a new data center construction project. Which of the following considerations falls specifically under the 'Environmental' pillar?

Question 3Choose one

In an Agile software project, the team uses a visual chart to track the amount of work remaining in the sprint versus the time remaining. This helps them predict if they will complete the sprint goal. What is this chart called? xychart-beta title "Sprint Progress" x-axis [Day 1, Day 2, Day 3, Day 4, Day 5] y-axis "Story Points" line [40, 32, 25, 15, 5] line [40, 30, 20, 10, 0]

Question 4Choose one

A project team is implementing Infrastructure as Code (IaC) to automate server provisioning. Which of the following is a PRIMARY benefit of this approach compared to manual configuration?

Question 5Choose one

**Case Study** **Scenario:** TechFlow Solutions is updating its legacy CRM system. The project has a strict budget of $500,000 and a 6-month timeline. The team decided to use a hybrid approach: Waterfall for the infrastructure setup and Agile for the software customization. Two months into the project, the infrastructure phase is complete but $50,000 over budget due to unexpected hardware price increases. The software team has started their first sprint but is reporting that the requirements from the sales department are vague and constantly changing. The Project Sponsor is concerned about the budget overrun and the potential for scope creep in the software phase. They have asked the Project Manager (PM) for a remediation plan. **Question:** Which strategy represents the BEST course of action for the Project Manager to address the budget overrun and scope risks simultaneously?

Question 6Choose one

A project manager calculates the Earned Value (EV) metrics for a project and finds the Schedule Performance Index (SPI) is 0.85 and the Cost Performance Index (CPI) is 1.10. What does this indicate about the project status?

Question 7Choose one

The following PowerShell command is used to create a new resource group in Azure as part of a project automation script: `New-AzResourceGroup -Name 'ProjectAlphaRG' -Location '______'` Which value represents a valid Azure region format to fill the blank?

Question 8Choose one

Which of the following documents is created during the Project Initiation phase and formally authorizes the project manager to apply organizational resources to project activities?

Question 9Choose one

A project manager is working with a distributed team across three time zones. The team finds that email threads are becoming unmanageable for tracking decision history. Which tool would BEST improve asynchronous collaboration and preserve decision context?

Question 10Choose one

In a matrix organization, a project manager is struggling to get commitment from a key technical resource who is also assigned to operational support tickets. The resource manager keeps pulling the engineer away for 'urgent' issues. Which conflict resolution technique should the project manager use FIRST to address this structural issue?

Question 11Choose one

A project manager is identifying risks for a new e-commerce platform. Which of the following is considered an 'Internal' risk?

Question 12Choose one

Which diagram BEST illustrates the dependencies between project activities and is used to calculate the Critical Path? graph LR Start((Start)) --> A[Task A: 5d] Start --> B[Task B: 3d] A --> C[Task C: 4d] B --> C C --> End((End))

15 more free samples are waiting