What is the primary function of the `it_pps_admin` role in the ServiceNow PPM suite?
A project manager needs to create a new Cost Plan for a project to track anticipated hardware expenses. The project is using multi-currency, with the project's functional currency set to EUR, but the hardware will be purchased in USD. How does the system determine the cost in the project's functional currency (EUR)?
To enable the full capabilities of the PMO Dashboard, including trend analysis and detailed performance metrics, which plugin must be installed and configured?
A user with only the `resource_user` role is attempting to create a resource plan for a project. They are unable to do so. Why is this expected behavior?
True or False: A single project can be associated with multiple portfolios simultaneously.
A PMO director wants to establish a financial baseline for a critical project after the initial budget has been approved. What is the primary purpose of creating a financial baseline for a project? (Select TWO)
A project manager on a long-running project has set a dependency: Task B (Finish-to-Start) must start after Task A finishes. Task A's planned duration is 10 days. On day 3, the project manager realizes Task A will now take 15 days and updates the planned duration. If the project's calculation mode is set to Automatic, what is the immediate impact on Task B's planned start date?
**Case Study**: A healthcare organization, HealthFirst, is using ServiceNow PPM to manage the development of a new patient portal. Due to regulatory compliance, time tracking must be extremely accurate, and all time charged to the project must be approved by both the project manager and the resource's line manager. The organization has a rule that time sheets must be submitted weekly, by Friday at 5 PM. If a time sheet is rejected, it must be resubmitted within two business days. The system needs to automatically generate time sheets for all allocated project members at the beginning of each week. Currently, project managers are complaining that they have to manually remind their team members to submit time sheets, and line managers are often unaware that they have pending approvals. The PPM administrator has been tasked with automating this process as much as possible. Which configuration actions should the administrator take to address these issues?
A demand manager is reviewing the Demand Workbench. They want to filter the list of demands to show only those in the 'Screening' state that are assigned to the 'IT Infrastructure' portfolio. How can they achieve this and save the filter for future use?