Free sasm sample questions
The free SASM sample questions on this page each show the correct answer and explain it. They deal with facilitating ART events, using flow accelerators and coaching self-organizing teams. Answer each one first, then read the explanation to find your gaps.
Try them in the simulator Same questions, with study, timed and flashcard modes.
Showing 10 of 20 free sample questions.
The ART Sync meeting in SAFe serves as a critical event for managing progress and impediments. This event replaces which TWO separate events from previous versions of the framework? (Select TWO)
An Advanced Scrum Master is analyzing their team's flow metrics. They notice that the 'Flow Load' metric is consistently high. What does this indicate about the team's process? ``` Flow Metrics - Team Hydra -------------------------- Flow Velocity: 8 stories/iteration (avg) Flow Time: 12 days (avg) Flow Load: 24 stories (avg) ```
A team on an ART is responsible for a critical shared service. Other teams frequently complain that this team is a bottleneck. The service team argues they are working at 100% capacity and cannot go faster. What is the most likely underlying cause of the bottleneck, according to flow principles?
The five dimensions of a Built-in Quality culture are Flow, Architecture & Design Quality, Code Quality, System Quality, and _________.
True or False: The primary purpose of the IP (Innovation and Planning) Iteration is to serve as a buffer to finish any work that did not get completed during the standard Iterations of the PI.
**Case Study:** An e-commerce ART, 'CheckoutFlow', is preparing for its quarterly PI Planning. In the lead-up, the Product Management team has identified over 100 potential features for the upcoming PI. The teams feel overwhelmed by the sheer volume and lack of clear priority. During backlog refinement sessions, discussions are unfocused, and there is no consensus on what the most important outcomes for the next PI should be. The RTE is concerned that the PI Planning event will be chaotic and unproductive. As an Advanced Scrum Master coaching the ART, you observe this breakdown in the 'Continuous Exploration' part of the Continuous Delivery Pipeline. The process lacks a mechanism to synthesize ideas into a coherent vision and roadmap for the upcoming PI. What is the most critical SAFe artifact or event that is likely missing or being performed ineffectively, which the Scrum Master should help Product Management implement?
A conflict arises between two teams on the ART. Team A believes Team B is not providing adequate support for a shared API, causing delays. Team B claims Team A is using the API incorrectly and not following the documentation. The conflict is escalating, and both teams' Scrum Masters are unable to resolve it. What is the most appropriate next step for an Advanced Scrum Master to take?
Which of the following metrics is a direct measure of an ART's predictability?
To improve the flow of value, an ART is focused on reducing the size of work items. Which statement best describes the relationship between transaction cost and holding cost when optimizing batch size?