Question 1Choose one

A Scheduling Professional is establishing the scheduling approach for a complex infrastructure project with high regulatory compliance requirements. The project charter dictates strict adherence to a fixed deadline due to government funding. Which scheduling methodology should be selected to best manage the critical path while ensuring all regulatory activities are documented and tracked?

Question 2Choose one

During the development of the Schedule Management Plan, the team is defining how schedule contingencies will be handled. Which component of the plan should explicitly detail the procedures for accessing management reserves versus contingency reserves?

Question 3Choose one

True or False: In Rolling Wave Planning, work to be performed in the near term is planned in detail, while work in the future is planned at a higher level of the WBS.

Question 4Choose one

A project manager is determining the appropriate level of accuracy for activity duration estimates during the initiation phase. Which of the following ranges typically represents a Rough Order of Magnitude (ROM) estimate?

Question 5Choose 2

You are decomposing the project scope to create the schedule. Which TWO items are primary outputs of the 'Define Activities' process? (Select TWO)

Question 6Choose one

An organization requires that all schedule variances exceeding 10% be reported to the steering committee. In which document should this threshold be explicitly defined?

Question 7Choose one

A scheduler is advising a project team on setting up their schedule model. The project involves high uncertainty and evolving requirements. Which scheduling approach would allow for high-level planning of the overall timeline while detailing only the immediate iteration?

Question 8Choose one

Consider the following network diagram logic: Activity A (5 days) -> Activity B (4 days) Activity A (5 days) -> Activity C (6 days) Activity B (4 days) -> Activity D (5 days) Activity C (6 days) -> Activity D (5 days) What is the Free Float of Activity B?

Question 9Choose one

When defining activities for a new software module, the team identifies a 'Finish-to-Start' relationship between 'Code Module' and 'Test Module'. However, the testing team states they can begin testing the initial components 2 days before coding is fully complete. Which dependency modification best represents this scenario?

Question 10Choose one

You are using the Three-Point Estimating (Beta/PERT) technique. An activity has an Optimistic estimate of 4 days, a Most Likely estimate of 7 days, and a Pessimistic estimate of 16 days. What is the expected duration?