Free CPCM sample questions
Real questions from the Certified Professional Contracts Manager practice bank, with the correct answer and an explanation for each one. No junk, no filler.
Try them in the simulator Same questions, with study, timed and flashcard modes.
Showing 10 of 20 free sample questions.
A federal agency is procuring cloud computing services and intends to award a multi-year contract. The requirements document emphasizes the need for cost efficiency and ensuring the government benefits from commercial price reductions over the life of the contract. Which contract clause would best achieve this objective?
During a source selection for a research and development contract, the Source Selection Authority (SSA) is presented with two proposals. Proposal A has a significantly higher technical rating but is 20% more expensive than Proposal B. The solicitation stated that technical factors are significantly more important than cost. According to FAR Part 15, what is the key determination the SSA must document to justify awarding to Proposal A?
A contract manager is leading a newly formed integrated project team (IPT) for a high-visibility acquisition. The team includes members from contracting, program management, legal, and engineering, who have never worked together. The manager observes conflict and a lack of clear direction. According to the Tuckman model of group development, which leadership style is most effective during this 'Storming' phase?
A contractor performing a cost-reimbursement contract submits an invoice that includes costs for extravagant holiday parties for its employees. The Defense Contract Audit Agency (DCAA) is most likely to question these costs based on which principle from FAR Part 31, Contract Cost Principles and Procedures?
A contract for custodial services is up for renewal. The contracting officer is analyzing the current process and wants to improve efficiency and reduce administrative burden. The current process involves numerous individual task orders and complex invoicing. Which of the following management techniques would be most effective in streamlining this type of service contract?
True or False: A contractor who discovers a latent ambiguity in a contract specification after award is generally entitled to an equitable adjustment for the increased costs of performance, provided they acted reasonably in their interpretation.
A contract manager is developing a lessons learned repository to comply with the 'Learn' domain of the CMBOK. Which of the following activities are essential components of an effective knowledge management system in a contracting organization? (Select THREE)
A project is terminated for the convenience of the government. The contractor submits a settlement proposal. Which of the following costs would be generally UNALLOWABLE in the termination settlement?
**Case Study** A large construction firm, BuildWell Inc., holds a Firm-Fixed-Price (FFP) contract with a federal agency to build a new research facility. The contract includes a standard 'Differing Site Conditions' clause (FAR 52.236-2). During excavation, BuildWell encounters a large formation of bedrock that was not indicated in the geotechnical survey provided in the solicitation documents. Removing the bedrock will significantly increase the cost and time to complete the project. BuildWell's project manager immediately notifies the on-site government representative via email. The following week, BuildWell submits a formal Request for Equitable Adjustment (REA) for the projected increase in costs and a 60-day schedule extension. The Contracting Officer (CO) is now reviewing the request. Which of the following is the CO's most appropriate action under the terms of the contract?