Question 1Choose one

A software development team is focused on technical excellence and wants to adopt an Agile practice that emphasizes continuous integration, test-driven development (TDD), and pair programming. Which Agile method most strongly advocates for these specific technical practices?

Question 2Choose one

True or False: The Scrum Master is accountable for the successful delivery of the product Increment and must approve it during the Sprint Review.

Question 3Choose one

A newly formed Scrum team has completed three Sprints. The number of story points completed in each Sprint was 15, 20, and 19 respectively. Based on this data, what is the team's calculated average velocity, which can be used for forecasting in the next Sprint Planning?

Question 4Choose one

What is the recommended timebox for a Daily Scrum event, regardless of the length of the Sprint?

Question 5Choose 3

A Product Owner is refining the Product Backlog and wants to ensure the user stories are well-formed. They are using the INVEST acronym as a guide. According to the INVEST model for user stories, which of the following characteristics are essential? (Select THREE)

Question 6Choose one

A client wants to hire a software development agency to build a new product using Scrum. The client is concerned about budget overruns and wants a predictable cost, but the agency is concerned about fixed scope in an agile environment. Which type of contract would best suit this situation, balancing the client's need for budget control with the agency's need for flexibility?

Question 7Choose one

A retail company, 'FashionFast,' is using Scrum to develop its e-commerce platform. The team has a new Scrum Master who observes the Daily Scrum. The meeting consistently takes 30-40 minutes. Each Developer gives a detailed report of what they did yesterday and what they will do today directly to the Scrum Master. There is little interaction between Developers, and problem-solving discussions often derail the meeting. After the meeting, Developers frequently approach the Scrum Master individually to report impediments. The Scrum Master recognizes that the Daily Scrum is being run as a traditional status meeting. The primary goal of improving team collaboration and creating a daily plan is being missed. The Scrum Master wants to coach the team to run the event more effectively according to Scrum principles. What is the most effective initial step the Scrum Master should take to improve the Daily Scrum?

Question 8Choose one

A team needs to estimate a large Product Backlog with over 100 items for the first time to get a rough idea for a release plan. A detailed Planning Poker session for every item would be too time-consuming. Which estimation technique is most suitable for quickly getting a relative size estimate for a large number of items?

Question 9Choose one

During Sprint Planning, the team selects several high-priority Product Backlog Items. What is the primary purpose of crafting a Sprint Goal after selecting these items?

Question 10Choose one

A Scrum Team wants to visualize not only their progress within the Sprint but also any scope changes that occur, such as work being added or removed from the Sprint Backlog. Which information radiator is better suited than a simple Burn-down chart for visualizing both work completion and scope changes over time?