Free RE18 sample questions
Use these free RE18 sample questions, each with an answer and an explanation, to check your requirements skills. They cover elicitation, requirement types and validation. Note any topic you miss and look it up in the current syllabus.
Try them in the simulator Same questions, with study, timed and flashcard modes.
Showing 10 of 20 free sample questions.
A business analyst has interviewed project stakeholders and has a robust list of requirements. At which stages in the requirements engineering framework would he check that these requirements support the business objectives defined at the start of the project?
A business analyst has collected the following legal requirement in support of a project seeking to improve the services provided by a children's charity: The system must record all the details of the children and young people we interact with. The project is in the early phases of requirements elicitation. At this stage, the business analyst is trying to ensure that they have captured the broad requirements. Which style of requirements document is the business analyst constructing, and what additional (essential) attribute will they need to record?
A set of requirements for a new online health information portal have been prioritized using MoSCoW: REQ#1: (S) REQ#2: (C) REQ#3: (S) REQ#4: (M) REQ#5: (M) REQ#6: (C) REQ#7: (W) Only the minimum usable subset was approved for inclusion in the first iteration of the project. After the build for the first iteration began, it was estimated there was enough time to add two additional requirements, without negative impact on the project schedule. Which two requirements will now be added to the first iteration build?
A project, which was initiated several months ago, has been impacted by the following changes: 1. An organizational restructure has altered the responsibilities of the stakeholders. 2. A new chief executive has been appointed, who has new ideas regarding the immediate focus of the project. Which of the following attributes in a requirements catalogue entry would need to be updated to reflect these changes?
A business analyst is concerned that the project team may not have a consistent understanding of the requirements set, as project team members have been working on their own individual tasks. He wants to ensure that the whole team is on track and is willing to take the time needed to achieve this. He does not want to involve business stakeholders, nor embarrass any of the project team. To begin the process of improving team understanding, he wants to hold a meeting to explain and present his understanding of the requirements to the team, and to hear their thoughts and ideas about his work so far. Which of the following approaches to requirements validation will he be using?
A zoo is in the process of introducing a new IT system to improve its processes and drive greater efficiency in its operations. It has received permission from the board of directors for a phased approach to introduce new business functionality and to replace manual processes with digital solutions. The key areas for inclusion in the first phase are a new animal health monitoring system, which will allow the zookeepers to utilize the power of data analytics to monitor and proactively manage the health of the animals. It will also provide them with a way of accurately recording the birth of new animals and record loans of animals to other zoos around the world. On the public-facing side, the project will provide customers with an adoption scheme, which will raise much-needed funds. A business analyst has constructed a use case diagram for the zoo: The following potential statements have been made about the diagram: A) The diagram is a correct representation of the scenario. B) There are aspects of the scenario which are incorrectly represented in the diagram. C) There are aspects of the scenario which are incorrectly omitted from the diagram. D) The notation used in the diagram is incorrect. Which of them is/are true?

A project sponsor has been asked to validate requirements in the requirements validation stage of the requirements engineering framework. The primary validation role of the project sponsor is to ensure that the requirements are what at this stage?
ChemCo Ltd has initiated a project to consider changes in its pension scheme. Paul works in the marketing department and is enrolled in the pension scheme. He has been invited to attend a pension scheme project session designed to elicit requirements, understand opinions on the level of service, and consider how it could be improved in the future. On arrival at the session, Paul recognizes people from other departments, who are all customers of the pension scheme. In which type of session is Paul about to participate?
The diagram below shows the relationship between requirements in a project. What does this diagram represent? graph TD subgraph Business Level BO1[Increase member retention by 10%] end subgraph Solution Level SR1[System shall send automated overdue reminders] SR2[System shall allow online renewal of items] end subgraph Implementation Level UC1[Use Case: Renew Item] TC1[Test Case: Verify renewal] end BO1 --> SR1 BO1 --> SR2 SR2 --> UC1 UC1 --> TC1
10 more free samples are waiting
Create a free account to unlock the whole RE18 sample bank, or get full access to all 153 practice questions in the simulator.