Question 1Choose one

What are the major disadvantages of having an improvement team that is too large?I. Difficulty in having constructive input from the entire group.II. Difficulty in arriving at consensus.III. Difficulty in finding large meeting facilities.IV. Difficulty, on the part of the recorder, in keeping up with more paperwork.

Question 2Choose one

Which of the following is NOT considered a prevention cost?

Question 3Choose one

An improvement in quality costs is MOST clearly indicated when:

Question 4Choose one

During the building phase of improvement team development, which of the following properly describes team activities?I. The team leader is usually directive.II. The team leader often delegates tasks.III. Team members prioritize and perform duties.IV. Team members are uncertain of their duties.