Question 1Choose one

How would a master production schedule (MPS) be used in an assemble-to-order (ATO) manufacturing environment? A.The MPS is used to plan subassemblies and components; end items are only scheduled when a customer order is received.B.Subassemblies are scheduled in the MPS when the customer order is received, and production can start.C.Typically, the MPS is not used in companies using an ATO manufacturing strategy.D.Often in an ATO environment, the MPS is created once a year and only revised if a product is discontinued.

Question 2Choose one

Price negotiation is most appropriate when purchasing which of the following product categories? A.CommoditiesB.Standard productsC.Items of small valueD.Made-to-order (MTO) items

Question 3Choose one

A part is sold as a service part, and it is also used as a component in another part. Which of the following statements about the planning for this part is true? A.Its low-level code is zero.B.The material requirements for the part will be understated.C.The service part demand can be included in the gross requirements.D.It shouldn’t have any safety stock.

Question 4Choose one

For a company that uses first in, first out (FIFO) inventory accounting, the actual use in production of a recently arrived shipment of more expensive components rather than lower-cost components previously received will have which of the following results? A.Higher cost of goods sold (COGS)B.Lower COGSC.No change to COGSD.A violation of FIFO rules

Question 5Choose one

What is the main negative effect of changing the due dates of open orders? A.The schedule information becomes inaccurate.B.The customer service level decreases.C.It leads to “nervousness” in the schedule.D.The schedule does not support demand.