Free CPIM sample questions

Each free CPIM sample question below has its answer and an explanation. You will see sales and operations planning, master scheduling, MRP and inventory policy. Try them to check your planning basics before you start the full practice test.

Try them in the simulator Same questions, with study, timed and flashcard modes.

Showing 5 of 10 free sample questions.

Question 1Choose one

The question below is based on the following information:Work Center 1 has an available capacity of 1,200 hours per month. Which of the following amounts represents the cumulative difference between the required capacity and the available capacity of Months 1 through 3? A.50B.150C.1,250D.3,750

Question 2Choose one

Which of the following statements about demonstrated capacity is true? A.It reflects the future load.B.It should be higher than rated capacity.C.It considers utilization and efficiency factors.D.It is determined from actual results.

Question 3Choose one

A plant uses a level production strategy due to the high costs of hiring and letting go of skilled employees. The constrained resource is due to be upgraded in the fourth month of the planning horizon, and that will reduce capacity for that month by 17%.Which of the following actions would be appropriate in this situation to maintain current levels of customer service and gross margin? A.Increase planned production for the next three periods.B.Defer the upgrade to a period beyond the planning time fence.C.Increase planned production from the fifth period on.D.Defer the upgrade to the period in which the highest stock level is planned.

Question 4Choose one

A company that uses concurrent engineering is likely to experience which of the following outcomes in the first period of a product's life cycle? A.Fewer product design changesB.An increase in obsolete inventoryC.More accurate forecastingD.Conflicts between purchasing and engineering

Question 5Choose one

One of the benefits of integrating a poka-yoke into the production process is that it can be used to: A.facilitate mixed-model scheduling.B.prevent defects.C.improve machine utilization.D.enable one-piece flow.

5 more free samples are waiting

Create a free account to unlock the whole CPIM sample bank, or get full access to all 90 practice questions in the simulator.